Planning Application

The planning process timeline shows both stages already completed and the next couple of stages to come.

Planning application timeline

May 2025

Planning consent approved

Planning Inspectorate upholds the Developer’s appeals and planning consent approved

November 2024

Planning Inquiry 

Planning Inquiry to open

Spring 2024

Planning Inspector appointed

Planning Inspector appointed, following Appeal, to conduct planning Inquiry to make final decision on applications

February 2024

Developers appeal to Secretary of State 

Developers appeal to Secretary of State to avoid plans going back to Mayor for 2nd time

January 2024

Planning Committee approve plans

Planning committee approved revised  plans for 3rd time

November 2023

Grenfell Tower fire regulations

Grenfell Tower fire regulations require plans to be updated

July 2023

Committee approve revised plans

Planning committee approve revised plans drawn up following Mayor’s decision

February 2022

Developers resubmit plans

New plans shared with the community.

Read more ›

July 2021

Mayor of London says no to scheme

Mayor of London turns down two planning applications at hearing at GLA.

January 2021

GLA rests dates for Planning Hearing

GLA Planning Hearing confirmed to be in July 2021

February 2020

Awaiting decision by Mayor of London

Awaiting decision by Mayor of London whether to call in the decision.
January 2020

Planning committee meeting

Planning committee meet on 29th January 2020 and resolve to support Application A and B but reject Application C.
July 2019

Consultation on minor additions

Consultation on minor additions to planning applications.